The Canadian Space Agency (CSA) reported spending $1.16 billion in the 2025–26 fiscal year, its highest-ever annual outlay and almost twice what it spent the previous year, according to the agency's 2025–26 Departmental Results Report posted Nov. 6.
The agency had planned $834 million for the year but ended up $326 million over that figure. The largest single driver of the increase was a payment of $562.9 million made under Canada’s cooperation agreement with the European Space Agency (ESA); the CSA had originally planned $31.4 million for that line. The report says most of the difference—$528.5 million—came from a transfer from the Department of National Defence (DND) as an early measure under the Defence Industrial Strategy. That transfer was part of Canada’s $664.6 million commitment at ESA’s Bremen ministerial in November 2025, described in the report as Canada’s “largest-ever commitment” to ESA.
The CSA noted that as a cooperating state it gains access to ESA contracts roughly in proportion to its payments; the agency expects about 80 per cent of the ESA defence-related funding to return to Canadian industry through contract awards. Measured cumulatively since 2015–16, Canada’s industrial return coefficient stood at 0.74 at the end of March. The CSA’s target is 0.93 by March 2030 and the report attributes the low cumulative figure to “the significant and sudden increase in funding,” expecting the coefficient to climb as Canadian organizations win more ESA work. Sixty-five Canadian organizations participated in ESA-funded projects during the year.
The report records program-level progress and changes elsewhere. Canadarm3 work continued: in July 2025 the CSA advanced the arm’s detailed design and completed the critical review of the Gateway External Robotic Interfaces. The report notes that NASA announced on March 24 its intention to pause the Lunar Gateway and shift focus to the lunar surface; the CSA says it "intends to repurpose Canadarm3 investments to support the next phase of lunar exploration." Assets under construction on the CSA’s balance sheet rose by $259 million during the year, to $865.8 million at March 31, with Canadarm3 identified as the main asset being built.
The agency also adjusted multiple mission plans. The CSA terminated its WildFireSat contract with Spire Global Canada in April 2026 after a comprehensive review; the contract had been worth about $72 million. The report says the government is working with industry and stakeholders to continue developing the wildfire-monitoring mission. For RADARSAT, the government announced $47 million to build, test and launch an additional satellite for the RADARSAT Constellation Mission to speed delivery, most of that funding earmarked for parts.
Operational highlights include the RADARSAT Constellation Mission handling more than 500,000 imagery requests from federal users for maritime surveillance, disaster response and climate research. The CSA extended operations of SCISAT, Canada’s longest-running satellite, to 2028–29 and archived and validated 25 years of data from MOPITT, an instrument on NASA’s Terra satellite that stopped operating in April 2025.
On services and industry impact, the CSA counted 91 services to Canadians that depend on space data—below its target of 111 and the lowest figure in the three years covered. The Canadian space sector employed 14,622 people in 2024 and contributed $3.8 billion to gross domestic product, both above CSA targets. The report also notes contractual obligations of about $770 million for building assets through 2029–30, mostly for Canadarm3 and WildFireSat, as of March 31 (before WildFireSat’s contract termination).